Gas System Upgrades: 1/30 - 2/10

PSEG

Starting November 1st, PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of January 30th through February 10th on the following streets:

  • 1/30 & 1/31 - E. Orchard St. through Franklin Turnpike to End
  • 2/1 & 2/2  - Berkshire Pl. through Arcadia Road to Crescent Blvd
  • 2/3 to 2/7 - Crescent Bend through Powell Rd to Arcadia  
  • 2/8 - Elm Street through Maple Street to Franklin Turnpike
  • 2/9 & 2/10 - W. Allendale Ave through Delta Court to W. Crescent Ave.

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****

Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com