Gas System Upgrades: 3/13 - 3/24

PSEG

Starting November 1st, PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of March 13th through March 24th on the following streets

  • 3/13 - Kayeton Rd through Wilton Dr to Harreton Rd.
  • 3/13 - Cannan Pl through Edgewood to Carteret
  • 3/14 - Beresford Rd through Crescent Ave to Schuyler Rd
  • 3/14 & 3/15 Overlook Ct. through E. Crescent Ave to End
  • 3/15 - Schuyler Rd through Stone Fence Dr. to Newton Pl
  • 3/16 - Newton Pl through Carteret Rd to Schuyler Rd
  • 3/17 - Carteret Rd through Newton Pl to Stone Fence Rd
  • 3/20 to 3/24 - Stone Fence Rod through Carteret Rd to End  

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****

Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com