Gas System Upgrades: 5/1 - 5/12
Posted on: May 1, 2023 - 9:17am
Starting November 1, 2022 PSE&G has begun work in Allendale to replace old gas pipes.
PSE&G has notified the Borough that work will be happening the weeks of May 1st through May 12th on the following streets
- 5/1 - Arcadia Rd through N. Franklin Tpke to Crescent Bend.
- 5/1 to 5/5 - Elbrook Dr to Hillside Ave
- 5/2 & 5/3 - Berkshire Pl through Arcadia Rd. To Crescent Bend.
- 5/4 to 5/8 - Crescent Bend through Arcadia Rd. to Powell Rd.
- 5/8 - Thomas St. through Hillside Ave to W. Maple
- 5/9 - Walnut Pl. Through Brookside to Oak St.
- 5/9 & 5/10 - Elm St through Maple St. to Franklin Tpke.
- 5/10 to 5/12 - E. Orchard St. through Franklin Tpke.
****Schedule is a preliminary schedule and may change depending on site conditions or weather.****
Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com