Starting November 1, 2022 PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of May 15th through May 26th on the following streets

  • 5/15 - Orchard St. through Franklin Tpke. 
  • 5/16 - Thomas St. through Hillside to W. Maple
  • 5/17 - Elbrook Dr. to Hillside Ave. 
  • 5/18 to 5/23 - Colonial Dr. through Forest Ave. to Surrey Ln.
  • 5/24 to 5/26 - Dogwood Dr. to Colonial Dr. 

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****