Gas System Upgrades: 2/27 - 3/13

PSEG

Starting November 1st, PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of February 27th through March 13th on the following streets

  • 2/27 - Schuyler Rd through Stone Fence Dr. to Newton Pl.
  • 2/27 & 2/28 - Meeker Ave through Franklin Tpk. to End 
  • 2/28 - Beresford through Crescent Ave to Schuyler
  • 2/27 & 3/3 - Stone Fence Rd through Carteret Rd to End
  • 3/1 - Carteret Rd through Newton Pl to Stone Fence Rd.
  • 3/1 to 3/3 - Wilton Dr. through E. Crescent Ave to Kayeton Rd. 
  • 3/2 - Stone Fence Rd through Carteret Rd to End
  • 3/3 - Carteret rd through Newton Pl to Stone Fence Rd. 
  • 3/6 to 3/8 -  Kayeton Rd through Wilton Dr to Harreton Rd.
  • 3/9 to 3/13 - Stone Fence Rod through Carteret Rd to End  

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****

Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com