Gas System Upgrades: 3/6 - 3/17

PSEG

Starting November 1st, PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of March 6th through March 17th on the following streets

  • 3/6 - Canaan Pl though Edgewood Rd to Carteret Rd. 
  • 3/7 - Beresford Rd. through Crescent Ave to Schuyler Rd.
  • 3/6 & 3/7 - Wilton Dr. though E. Crescent Ave. to Kayeton Rd.
  • 3/8 -  Schuyler Rd. through Stone Fence Dr. to Newton Pl.
  • 3/9 - Newton Pl through Carteret Rd to Schuyler Rd 
  • 3/8 to 3/10 -  Kayeton Rd through Wilton Dr to Harreton Rd.
  • 3/10 - Carteret Rd through Newton Pl to Stone Fence Rd
  • 3/13 - Wilton Dr. through Kayeton Rd to Gloria Dr.  
  • 3/14 t& 3/15 Overlook Ct. through E. Crescent Ave to End
  • 3/13 to 3/17 - Stone Fence Rod through Carteret Rd to End  

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****

Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com