Gas System Upgrades: 4/17 - 4/28

PSEG

Starting November 1, 2022 PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of April 17 through April 28 on the following streets

  • 4/17 to 4/19 - Colonial Dr. through Forest Rd to End
  • 4/17 to 4/19 - Kayeton Rd. through Wilton Dr. to Harreton Rd.
  • 4/17 to 4/21 - Arcadia Ct. through N. Franklin Tpke to Cresent Rd.
  • 4/20 - Thomas St. through Hillside Ave to W. Maple Ave. 
  • 4/20 & 4/21 - Meeker Ave. to  Franklin Tpke
  • 4/21 - Walnut Pl. through Oak St. to Walnut St. 
  • 4/24 - 1st St. through Cebak Ct. to Mallinson St. 
  • 4/24 to 4/28 - Berkshire Pl. through Arcadia Rd. to Cresent Rd. 

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****