Gas System Upgrades: 4/24 - 5/5

PSEG

Starting November 1, 2022 PSE&G has begun work in Allendale to replace old gas pipes.

PSE&G has notified the Borough that work will be happening the weeks of April 24th through May 5th on the following streets

  • 4/24  - Thomas St through Hillside Ave to W. Maple Ave.
  • 4/24 to 4/27 - Berksire Pl through Arcadia Rd to Cresent Rd.
  • 4/24 & 4/25 - Meeker Ave. to Franklin Tpke
  • 4/25 - Walnut Pl. through Oak. St. to Walnut Pl. 
  • 4/26 - 1st St. through Cebak Ct. to Mallinson St. 
  • 4/27 & 4/28 - E. Orchard through Crescent to End
  • 4/28 - Arcadia Ct. through N. Franklin Tpke to Cresent Rd
  • 5/1 to 5/4 - Crescent Bend through Arcadia Rd. to Powell Rd. 
  • 5/5 - Elm St through Maple St to Franklin Tpke

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****

Below are informational documents from PSE&G detailing this project.
Questions should be sent to PSE&G via:
Phone:1-833-661-6100
email: gasworks@pseg.com