Gas System Upgrades: Milling & Paving Schedule

PSEG

PSE&G has notified the Borough that as part of the gas system upgrade project, milling and paving work will be occurring from November 6th to November 21st on the following streets:

  • Edgewood Rd between Schuyler Rd & Brookside Ave:  Milling Date 11/6 - Pave Date 11/13
  • Canaan Pl between Edgewood Rd & Carteret Rd:  Milling Date 11/6 - Pave Date 11/13
  • Newton Pl between Schuyler Rd & Carteret Rd:  Milling Date 11/6 - Pave Date 11/13
  • Carteret Rd between Newton Pl & Carteret Ct:  Milling Date 11/6 & 11/7 - Pave Date 11/13 & 11/16
  • Carteret Ct between Carteret Rd to End:  Milling Date 11/7 - Pave Date 11/16
  • Stone Fence Rd to End:  Milling Date 11/7 & 11/8 - Pave Date 11/16
  • Schuyler Rd between Stone Fence Rd & Newton Pl:  Milling Date 11/8 - Pave Date 11/17
  • Beresford Rd between Schuyler Rd & W Crescent Ave:  Milling Date 11/8 - Pave Date 11/17
  • Brookside Ave between Park Ave & W Crescent Ave:  Milling Date 11/9 - Pave Date 11/14
  • Walnut Pl between Brookside Ave to End:  Milling Date 11/9 - Pave Date 11/14
  • Forest Rd between Macintyre Ln & Hillside Ave:  Milling Date 11/9 & 11/10 - Pave Date 11/15\
  • Elbrook Dr between Hillside Ave & Hillside Ave:  Milling Date 11/13 - Pave Date 11/14
  • Thomas St between Hillside Ave & W Maple Ave:  Milling Date 11/13 - Pave Date 11/15
  • Klomburg Dr between W Crescent Ave to End:  Milling Date 11/13 - Pave Date 11/17
  • W Allendale Ave between Delta Ct & W Crescent Ave:  Milling Date 11/13 & 11/14 - Pave Date 11/17
  • Erold Ct between Chestnut St to End:  Milling Date 11/14 - Pave Date 11/20
  • Homewood Ave between Franklin Tpke to End Trench:  Milling Date 11/14 - Pave Date 11/17
  • E Orchard St between Franklin Tpke to End Trench:  Milling Date 11/14 - Pave Date 11/20
  • Arcadia Pl between Franklin Tpke to End:  Milling Date 11/14 & 11/15 - Pave Date 11/20
  • Berkshire Pl between Crescent Bnd & Arcadia Pl:  Milling Date 11/15 - Pave Date 11/20
  • Crescent Bnd between Powell Rd & Arcadia Pl:  Milling Date 11/15 & 11/16 - Pave Date 11/21
  • Kayeton Rd between Wilton Dr & Harreton Rd:  Milling Date 11/16 - Pave Date 11/21
  • Wilton Dr between Kayeton Rd & E Crescent Ave:  Milling Date 11/16 - Pave Date 11/21
  • Overlook Ct between E Crescent Ave to End:  Milling Date 11/16 - Pave Date 11/21

****Schedule is a preliminary schedule and may change depending on site conditions or weather.****